Resources | Subject Notes | Information Technology IT
This section details the use of Gantt charts and PERT charts as project management tools. These tools are essential for planning, scheduling, and monitoring projects effectively.
A Gantt chart is a visual representation of a project schedule. It displays tasks against a timeline, showing start and finish dates, durations, and dependencies. It's a simple and widely used tool for project planning.
The following is a simplified text-based representation of a Gantt chart. In practice, software provides a graphical representation.
Task | Start Date | Duration (Days) | End Date |
---|---|---|---|
Task A: Requirements Gathering | 2024-01-01 | 5 | 2024-01-05 |
Task B: Design | 2024-01-05 | 7 | 2024-01-12 |
Task C: Development | 2024-01-12 | 10 | 2024-01-22 |
Task D: Testing | 2024-01-22 | 5 | 2024-01-26 |
Task E: Deployment | 2024-01-26 | 2 | 2024-01-28 |
Figure: Suggested diagram: A simple Gantt chart showing tasks, start dates, durations, and end dates. The chart would visually represent the timeline of the project.
PERT (Program Evaluation and Review Technique) charts are used for project scheduling, especially when tasks have uncertain durations. Unlike Gantt charts which assume fixed durations, PERT charts use probabilistic estimates for task durations. They are particularly useful for projects with a high degree of risk.
PERT uses three estimates for each task duration:
The expected duration (te) of a task is calculated using the following formula:
$$te = \frac{a + 4m + b}{6}$$The following is a simplified text-based representation of a PERT chart. A graphical representation is typically used.
Figure: Suggested diagram: A PERT chart showing tasks, dependencies, and estimated durations. The chart would visually represent the project network and the critical path.
Task | Optimistic (a) | Most Likely (m) | Pessimistic (b) | Expected Duration (te) |
---|---|---|---|---|
Task A: Requirements Gathering | 5 | 7 | 10 | 7.33 |
Task B: Design | 7 | 9 | 12 | 9.00 |
Task C: Development | 10 | 12 | 15 | 12.33 |
Task D: Testing | 5 | 6 | 8 | 6.33 |
Task E: Deployment | 2 | 3 | 4 | 3.00 |
Critical Path: Based on the estimated durations, the critical path is A -> B -> C -> D -> E, with an expected duration of 31.33 days.
| Feature | Gantt Chart | PERT Chart |
Feature | Gantt Chart | PERT Chart |
---|---|---|
Duration Estimation | Fixed durations | Probabilistic durations (a, m, b) |
Complexity | Simpler to create and understand | More complex, especially for large projects |
Usefulness | Suitable for projects with well-defined tasks and durations | Suitable for projects with uncertain durations and high risk |
Both Gantt charts and PERT charts are valuable tools for project management. The choice of which to use depends on the specific characteristics of the project.